UPDATED ALIGNMENT: We've changed our pipeline location to Lendor Court, rather than Helen Court due to further investigation of underground services. 

Please do not park on the street during working hours (Monday to Friday 7am-6pm). This will help our crews install the pipeline as quickly as possible.

Additional impact: Footpath closure on Centre Dandenong Road from Chifley Drive to Grange Road day and night until late May. Bus stops not impacted. More information below.

There are night works from Sunday to Thursday between 7pm and 5am on:

  • Centre Dandenong Road, between Taunton Drive and Chifley Drive until late May

Where we will be working - West Connection Network

What we're doing

The scheme will involve the design and construction of a transfer main and 3 connection networks to bring recycled water from near the Eastern Treatment Plant to service around 40 commercial sites in the Bayside, Kingston, Greater Dandenong and Monash Local Government Areas. For information about the entire scheme visit Dingley Recycled Water Scheme.

The 13km West Connection Network extends from our Transfer Main in Old Dandenong Road to Black Rock and Beaumaris. The project has been awarded to our Industry Partner ABK (Abergeldie, BMD & KBR). 

We'll be working in works stages of around 100-200m to minimise long term impacts to residents and the community. We expect to spend about 1-2 weeks in each works stage, depending on the weather. We're working with Bayside City Council and the City of Kingston to minimise impacts to the community as best we can.

You might also see us working in other areas of the pipeline. Please take care when travelling around our construction sites. See a map of the entire project alignment on the project homepage.

We'll letter drop affected residents and businesses before we start works in each area. UPDATED ALIGNMENT: We've changed our pipeline location to Lendor Court, rather than Helen Court due to further investigation of underground services. We'll attempt to contact residents near our new works area. The additional drilling works on Lendor Court will commence on Wednesday 1 April however we may have a presence in the area as we scope the new alignment before drilling commences.

When we’ve finished, we’ll return any areas we’ve impacted as close as possible to their original condition.

When it's happening

We started works in late July along Cheltenham Road, see our progress on the map above. From 16 March, we'll start working in the day on Renowden Street.UPDATED ALIGNMENT: We've changed our pipeline location to Lendor Court, rather than Helen Court due to further investigation of underground services. We'll attempt to contact residents near our new works area. The additional drilling works on Lendor Court will commence on Wednesday 1 April however we may have a presence in the area as we scope the new alignment before drilling commences.

Working hours are Monday to Friday between 7am and 6pm. Occasionally, we may have to work at other times. This will include:

Night works from Sunday to Thursday between 9pm and 5am on:

  • Centre Dandenong Road, between Taunton Drive and Chifley Drive until late May
    • between Kingston Central Boulevard and Chifley Drive for approximately 8 weeks

    • between Taunton Drive and Kingston Central Boulevard for approximately 3 weeks

One night in early 2026 between 6.30pm and 5am, pending weather, permits and other authority works on:

  • Latrobe Street at the rail crossing

We'll notify residents and businesses when we schedule these works.

We might also have to work on Saturdays, between 7am and 5pm, depending on our progress.

If we do need to work on Saturdays, we'll let the area know via SMS and email. Check your contact details are up to date on your mySouthEastWater account.

We expect recycled water to flow to all sites before 2028.

What might impact you

We’ll do our best to keep impacts to a minimum, however these are the kinds of things you might notice while we work:

  • Lane closures
  • Less car parks in the area
  • More trucks in the area
  • Noise from heavy machinery, such as saw cutting, grinding and beepers when trucks reverse
  • Some road closures when we work at night
  • Lights when we work at night

We have night works on Centre Dandenong Road, Voltri Street and Grange Road. We'll start with service proving, then construction, temporary reinstatement and then permanent reinstatement. 

Traffic impacts during Centre Dandenong Road works:

  • Full road closure from 9pm to 5am Sunday to Thursday (see below map)
  • Footpath closure between Chifley Drive and Grange Road both day and night from 22 March. This is because of a change in the location we need to install the pipeline
  • Buses and bus stops are not impacted and will operate as normal

Our team will be around during working hours to make sure people, bikes and cars can move around safely. Please take care when travelling around the work sites.

Buses will not be impacted.

Don't miss these details

ABK will have a temporary storage area for a small office and equipment. This area has been approved by council. You'll notice a site office that looks like a shipping container as well as temporary fencing around the area.

ABK will be using their Program Office on Tootal Road, Dingley Village for material drop off and pick up during night works.

Locals will still have property access throughout the works. However, there may be traffic delays of up to 5 minutes during working hours.

Please obey no parking signage and bollards in the area so we can get the job done as quickly as possible.

You shouldn’t notice any change to your water or sewer services while we work. 

Centre Dandenong Road night works

All businesses and properties will be accessible throughout the works, including Revo Fitness and Guzman y Gomez. You may have to enter from either Warrigal Road or Boundary Road onto Centre Dandenong Road, depending on the stage of works.

Construction and drilling iis until late May.

East stage - around 8 weeks

Between Kingston Central Boulevard and Chifley Drive

West stage - around 3 weeks

Between Taunton Drive and Kingston Central Boulevard

What you might hear and see

Frequently Asked Questions

The Dingley Recycled Water Scheme will deliver recycled water to around 40 sites in the Bayside, Kingston, Greater Dandenong and Monash Local Government Areas.

Supplying recycled water to local parks, world-class golf courses, sporting ovals, laundromats, market gardens and nurseries, the scheme will help preserve our drinking water supply, and help our communities become more resilient to climate change.

Works wil involve installing recycled water pipes, usually under the road. We'll be working in works stages of around 100-200m to minimise long term impacts to residents and the community, starting in Cheltenham Road. We expect to spend about 1-2 weeks in each works stage, depending on the weather. 

Abergeldie, BMD and KBR (ABK) will complete these works on behalf of South East Water.

We send digital communications to customers with a mobile number or email address registered to their mySouthEastWater account prior to works commencing. To register or check if your details are up to date visit my.southeastwater.com.au.

We then put a letter in your letter box before we commence works. If the works are deferred, we will send you another notification of the new proposed start date. Project signage will be installed at the work area prior to commencing the works. 

We will also keep information on this webpage updated throughout the project.

No, we don't plan to impact driveway access. If for any reason during construction we need to block your driveway access, we will notify you in person and where possible, provide at least 24 hours' notice so that alternative parking arrangements can be made.

To safely undertake these works, traffic and pedestrian conditions may change so please take care when travelling around the construction sites. 

No. If you experience any disruption to your water or sewerage services please call our 24/7 Faults and Emergencies team on 13 28 12.

When we’ve finished the job, we’ll leave things how we found them and return any areas we’ve impacted as close as possible to their original condition. 

Only high usage customers who have agreed to connect to the scheme will need to pay. Discussions with scheme customers on pricing will take place prior to connection. 

Need to get in touch?

We're here to help.

Dingley Recycled Water Scheme - West Connection Network

Contact us via phone

1800 330 129

Contact us via email

dingley@sew.com.au 

Contact us via post

Dingley Recycled Water Scheme
PO Box 2268
Seaford VIC 3198

Translator Interpreter Service
All languages 03 9280 0779

 

National Relay Service (NRS)
TTY: 13 36 77 (ask for 131 851)