Works in St Kilda West - Stage 2

 

You might not notice a lot of the work we do because most of it is beneath your feet. Every day, we’re maintaining and upgrading the pipes and pumps that keep the sewage network flowing.

With works in Deakin Street, Cowderoy Street, Canterbury Road and around Albert Park you might have seen us or our delivery partner ZJW (Zinfra, Jaydo, WSP Joint Venture) around.

Here’s what to expect while we get the job done.

 

What we're doing

The project will increase the capacity of the sewer network to cater for population growth in the area and future proof the sewerage system.

Stage 2a involved relining the existing sewer in early December 2024. Stage 2b will involve constructing the new sewer from 6 January 2025.

  • Stage 1 is in Albert Park (near Ross Gregory Oval)
  • Stage 2a was in Cowderoy Street
  • Stage 2b is in Deakin Street
  • Stage 3 is in Albert Park (near Hockey Drive)
  • Stages 4, 5 & 6 is in Union Street, St Kilda Road and Beatrice Street
When it's happening

We've been undertaking investigative works along the proposed alignment since mid-November 2022. Construction of the new sewer started in Albert Park in mid September 2024. We've now finished constructing the pipeline. In the coming months we'll undertake testing. We expect to finish the whole project by mid 2026.

Stage 2a in Cowderoy Street - completed
We successfully relined the existing sewer in Cowderoy Street in early December.

Stage 2b in Deakin Street  - completed
We started stage 2b in Deakin Street in January 2025.

We've installed the pipeline and have removed our site compound and equipment. We'll be back later in 2026 to undertake commissioning and decommissioning works.

Working hours are Monday to Friday between 7am and 6pm. On occasion we may need to work outside these hours for safety, technical or permit reasons.

Stages 4, 5 & 6

We've finished installing the pipeline in St Kilda Road, Union Street and Beatrice Street.

There will be no interruption to your water or sewer services while we work.

What might impact you

When we schedule commissioning and decommissioning works later in 2026 , we'll let you know what short term impacts to expect.

Thank you for your patience while we've been in the area.

Don't miss these details

We're working with Zinfra, Jaydo, WSP (ZJW) to help us complete this project. We'll be in touch when we schedule commissioning and decommissioning works.

You shouldn’t notice any change to your water or sewer services while we work.

When we’ve finished the job, we’ll leave things how we found them and make sure we return any areas we’ve impacted as close as possible to their original condition.

Where we're working

Frequently Asked Questions

We manage an infrastructure program which involves replacing, maintaining and upgrading the existing water and sewerage infrastructure above and below the ground, so you can always rely on us when you need a drink, a bath, to wash the clothes or dishes and every time you flush or send water down the drain.

 

There are more of us living in the Albert Park area now and, with potential storm surges, floods and extreme weather events from climate change, we need to make sure everyone is protected from sewage surges or overflows. Sewage surges or overflows happens when flooded sewerage pipes aren’t large enough and don’t have the pressure, to take sewage and additional storm water run-off to the local treatment plant.

We’ve awarded the contract to Zinfra, Jaydo, WSP Joint Venture (ZJW) 

South East Water and their appointed contractors will keep you informed about the project and construction in your area, and we’ll work with you to discuss your access needs before we start to build.

The new sewer pipes will be laid beneath the road or footpath, depending on the outcomes of geotechnical investigations and the location of utilities.  The pipes will be laid using trenchless technology, where shafts are dug, then bores are sunk, and pipes pushed through behind them. This is the best way to lay pipes in built up areas because it limits the disruption to the local community.

No, but please don't hesitate to call our 24/7  Faults and Emergencies team on 13 28 12 if you experience disruptions at any time.

Construction hours will be Monday to Friday between 7 am and 5 pm. On the odd occasion we may need to work at other times, including night works, for safety or technical reasons. If we do, we’ll make sure we let you know in advance so you can plan accordingly.

We'll endeavour to make sure your driveway isn’t blocked during construction, but if it is, we’ll let you know beforehand, so you have time to organise alternative parking. But don’t worry. We will be around to help you get out of your driveway in an emergency. 

We'll speak with you in the lead up to construction to understand more about your deliveries, waste removal and customer access, and work with you to make sure these are not impacted. If we do need to block your driveway for a short period of time, we’ll work out alternative arrangements with you prior to works commencing.

Prior to construction commencing we’ll be in touch to understand more about your parking arrangements. We do apologise if local parking is impacted but will work to make sure this is for as short a time as possible.

When we’ve finished the job, we’ll leave things how we found them and make sure we return any areas we’ve impacted as close as possible to their original condition.

No. There is no cost to the property or business owner for these works. 

Need to get in touch?

We're here to help.

Albert Park Branch Sewer Upgrade

Contact us via phone

1800 330 129

Contact us via email

engagement@sew.com.au 

Contact us via post

Albert Park Branch Sewer Upgrade
PO Box 2268
Seaford VIC 3198

Translator Interpreter Service
All languages 03 9280 0779

 

National Relay Service (NRS)
TTY: 13 36 77 (ask for 131 851)